Neighborhood Park on Carpenter Fire Station Road

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option
RSS
  • CFSR overview
  • CFSR Misting
  • CFSR Futsal
  • CFSR Rendering

Project Updates

Summer 2024 - Park Open
There is still some work occurring in select areas of the park but the majority of the park is ready for use!

The construction bid award for the park was approved by Council on March 10, 2022. Park construction began in May 2022 and opened in February 2024.

Project Scope

This neighborhood park creates a vibrant and lively space within a wooded setting, offering varying levels of recreation and social interaction ranging from organized sporting events, to informal play, to quiet and reflective spaces. A wide wooded buffer of existing and planted trees along the borders of the park will provide an attractive environment for park visitors and help shield neighbors from lights and noisy activities. The forested slopes at the southern edge of the park offer opportunities for enjoyment of nature as well as protection of water quality in Panther Creek. The program was selected to provide play opportunities for everyone - families, teens, and adults young and old.

  • Two lighted youth ballfields
  • Playground
  • Shelter, restroom and other shade structures
  • Dog park
  • Basketball/Futsal court
  • Activity nodes for teens
  • Adult fitness hub
  • Misting feature/sculpture as gateway to park’s center
  • Paved loop trails and link to Panther Creek Greenway
  • Extension of Panther Creek Greenway to link to Cameron Pond subdivision and to developer-built trail east of the park

Project Background

The 20.8-acre neighborhood park site is located at the southeast corner of Carpenter Fire Station Road and Highcroft Drive in Northwest Cary. Approximately 16.8 acres of the park land was obtained by a dedication from the Cameron Pond subdivision rezoning. The Town of Cary later purchased four additional residential parcels that front Carpenter Fire Station Road. 

Master planning for this park and the park on McCrimmon Parkway started in the fall of 2017. Public involvement included public information meetings in January and November of 2018; an online questionnaire for public input; a Citizens Resource Team which met three times to provide input on the proposed program and plans; and presentations to the Parks, Recreation and Cultural Resources and Public Art Advisory Boards. On June 27, 2019, the Cary Town Council approved the master plan and master plan report for the Neighborhood Park on Carpenter Fire Station Road along with the master plan for the park on McCrimmon Parkway. Construction funding for these parks is included in the Parks Bond approved by Cary voters in October 2019.

Project Cost and Schedule

Budget: $13,050,000 for design and construction. 

Funding comes from Recreation Payment In Lieu-West Funds and the Parks Bonds approved by voters in October 2019.

  • Spring 2022: Begin Construction
  • Summer 2024: Completion 